Invoicing - part completion of construction contracts
Question asked by Daniel Traynor 10 years ago
My client has an ongoing construction contract and is required to submit an invoice based on the certified point of completion, i.e. if 10% = £25k, £20% = £50k less £25k already invoiced.
The end client requires this all in one invoice and my client has been duplicating the revenue, so invoice 1 = £25k, invoice 2 = invoice 1 + new works @ £25k, invoice 3 = Invoice 1&2 @ £50k + new works at £X.
Does anyone have a better way of doing this? Any help appreciated.